Question 131

Which Knowledge Areas include processes from the Closing Process Group?

  1. Project Quality Management and Project Time Management
  2. Project Scope Management and Project Risk Management
  3. Project Stakeholder Management and Project Cost Management
  4. Project Integration Management and Project Procurement Management

Question 132

Stakeholder satisfaction should be managed as a key project:

  1. Benefit
  2. Initiative
  3. Objective
  4. Process

Question 133

Which cost is associated with nonconformance?

  1. Liabilities
  2. Inspections
  3. Training
  4. Equipment

Question 134

Which tool or technique of the Define Activities process allows for work to exist at various levels of detail depending on where it is in the project life cycle?

  1. Historical relationships
  2. Dependency determination
  3. Bottom-up estimating
  4. Rolling wave planning

Question 135

An output of the Create WBS process is:

  1. Scope baseline.
  2. Change requests.
  3. Accepted deliverables.
  4. Variance analysis.