Question 51
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
- Feedback analysis
- Stakeholder analysis
- Communication management plan
- Stakeholder management plan
Question 52
A method of obtaining early feedback on requirements by providing a working model of the expected product before actually building is known as:
- Benchmarking.
- Context diagrams.
- Brainstorming.
- Prototyping.
Question 53
Which stakeholder classification model groups stakeholders based on their level of authority and their active involvement in the project?
- Power/influence grid
- Power/interest grid
- Influence/impact grid
- Salience model
Question 54
Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?
- Facilitation techniques
- Expert judgment
- Analytical techniques
- Variance analysis
Question 55
Which basic quality tool is most useful when gathering attributes data in an inspection to identify defects?
- Control charts
- Pareto diagrams
- Ishikavva diagrams
- Checksheets