APM-001: Associate in Project Management
APM-001: Associate in Project Management practice questions, page 12 of 28, with answer review and explanations.
Question 56
The process of estimating the type and quantity of material, human resources, equipment, or supplies required to perform each activity is known as:
- Collect Requirements.
- Conduct Procurements.
- Estimate Activity Durations.
- Estimate Activity Resources.
Question 57
Which input to the Identify Stakeholders process provides information about internal or external parties related to the project?
- Procurement documents
- Communications plan
- Project charter
- Stakeholder register
Question 58
The Identify Stakeholders process is found in which Process Group?
- Initiating
- Monitoring and Controlling
- Planning
- Executing
Question 59
An input to Develop Project Charter is a/an:
- Business case.
- Activity list.
- Project management plan.
- Cost forecast.
Question 60
Which item is a formal proposal to modify any document, deliverable, or baseline?
- Change request
- Requirements documentation
- Scope baseline
- Risk urgency assessment