Question 46

Market conditions and published commercial information are examples of which input to the Estimate Costs process?

  1. Scope baseline
  2. Organizational process assets
  3. Enterprise environmental factors
  4. Risk register

Question 47

An output of the Develop Project Team process is:

  1. Organizational process assets.
  2. Enterprise environmental factors updates.
  3. Project staff assignments.
  4. Organizational charts and position descriptions.

Question 48

The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:

  1. Plan Human Resource Management.
  2. Acquire Project Team.
  3. Manage Project Team.
  4. Develop Project Team.

Question 49

Which item is an example of personnel assessment?

  1. Resource calendar
  2. Tight matrix
  3. Team-building activity
  4. Focus group

Question 50

The Plan Stakeholder Management process belongs to which Process Group?

  1. Executing
  2. Initiating
  3. Planning
  4. Monitoring and Controlling