Question 46
Market conditions and published commercial information are examples of which input to the Estimate Costs process?
- Scope baseline
- Organizational process assets
- Enterprise environmental factors
- Risk register
Question 47
An output of the Develop Project Team process is:
- Organizational process assets.
- Enterprise environmental factors updates.
- Project staff assignments.
- Organizational charts and position descriptions.
Question 48
The process of confirming human resource availability and obtaining the team necessary to complete project activities is known as:
- Plan Human Resource Management.
- Acquire Project Team.
- Manage Project Team.
- Develop Project Team.
Question 49
Which item is an example of personnel assessment?
- Resource calendar
- Tight matrix
- Team-building activity
- Focus group
Question 50
The Plan Stakeholder Management process belongs to which Process Group?
- Executing
- Initiating
- Planning
- Monitoring and Controlling