Question 41
Which input to the Plan Risk Management process provides information on high-level risks?
- Project charter
- Enterprise environmental factors
- Stakeholder register
- Organizational process assets
Question 42
Which input may influence quality assurance work and should be monitored within the context of a system for configuration management?
- Work performance data
- Project documents
- Scope baseline
- Requirements documentation
Question 43
Change requests are processed for review and disposition according to which process?
- Control Quality
- Control Scope
- Monitor and Control Project Work
- Perform Integrated Change Control
Question 44
The review of a sellers progress toward achieving the goals of scope and quality within cost and schedule compared to the contract is known as:
- Work performance information.
- Inspections and audits.
- Payment systems.
- Procurement performance reviews.
Question 45
The iterative and interactive nature of the Process Groups creates the need for the processes in which Knowledge Area?
- Project Communications Management
- Project Integration Management
- Project Risk Management
- Project Scope Management