Question 31
Before system operator training can begin, each facility alarm point should:
- allow flexible response times.
- have detailed operating procedures.
- integrate with other security equipment.
- list a generic response format.
Question 32
A principal goal of risk analysis is to:
- limit the impact of risk and legal exposure.
- balance the impact of risk against the cost of countermeasures.
- protect the enterprise from the risk of serious loss.
- reduce insurance premiums.
Question 33
Which of the following is an example of a preventative maintenance measure?
- Conducting periodic resistance testing
- Replacing hardware components to keep equipment up to current specifications
- Establishing a maintenance function that acts on and logs requests from users in the event of a system problem
- Reporting the problem and recommending resolutions
Question 34
Strategies to mitigate damage to communications systems include all of the following EXCEPT:
- emergency duress processes.
- replacement agreements.
- divergent routing.
- hot/cold sites.
Question 35
How an organization's human resources are managed will impact the success or failure of:
- recovery effects.
- effective management.
- risk assessment.
- crisis management.