Question 26
During final acceptance testing, physical security electronic system enclosures and cabinets with doors on hinges should be checked to ensure that they are equipped with:
tamper switches.
power interrupt switches.
appropriate labeling.
keyed locks.
Question 27
Which of the following is the first step of project management in the planning phase of the physical protection system life cycle?
Contract with a security consultant or designer to lead the process from inception to conclusion.
Conduct a security assessment to determine what vulnerabilities need to be mitigated.
Secure funding for the eventual project so size and scope can be determined based on the available funding.
Create a team that includes all stakeholders to develop the requirements.
Question 28
The five major criteria of a good security survey report are:
introduction, scope, survey drawings, scaled drawings, and conclusion.
cover letter, introduction, system block diagrams, cost estimate, and conclusion.
accuracy, precision, consistency, timeliness, and tone.
accuracy, clarity, conciseness, timeliness, and pitch.
Question 29
A security director uses a process that requires vendors to submit a technical proposal describing their understanding of the system objectives and how they will be met. The security director then selects a vendor based on the best value, rather than on the lowest qualified bid. What process is the security director most likely using?
Sole-source procurement
Request for proposal (RFP)
Request for quote (RFQ)
Invitation for bid
Question 30
Which of the following items are part of the planning phase of project management?