Question 21
What is the key concern when multiple Development Teams are working from the same Product Backlog?
- Minimizing dependencies between teams.
- Clear definition of requirements.
- Meeting original scope projections.
- Making sure there's enough work for everyone on every team.
- Maximizing velocity.
Question 22
What does it mean to say that an event has a time-box?
- The event must happen at a set time.
- The event must happen by a given time.
- The event must take at least a minimum amount of time.
- The event can take no more than a maximum amount of time.
Question 23
Which outcome is expected as Scrum Teams mature?
- They will improve their definition of ג€Doneג€ to include more stringent criteria.
- The Sprint Retrospectives will grow to be longer than 4 hours.
- There is no need for a time-boxed Sprint.
- Sprint Reviews will no longer be needed.
- A Scrum Master is no longer needed since they are a mature team now.
Question 24
When must a Scrum Team release each Increment?
- When it makes sense to release it.
- When the Scrum Team finishes their work.
- Whenever the product is free of defects.
- After every Sprint, without exception.
Question 25
A properly functioning Scrum Team will have at least one Release Sprint and may well have several.
- True
- False