Question 41

Which is a purpose of the Managing Product Delivery process?

  1. Enable the Senior Supplier to be provided with sufficient information by the Project Manager so that they can review the success of the current Work Package
  2. Provide a controlled link between the Project Manager and the Team Manager(s)
  3. Enable the Project Board to request updates to the current Team Plan
  4. Establish solid foundations for the project

Question 42

From whom does a Team Manager obtain approval for a completed product?

  1. Project Manager
  2. Project Support
  3. The authority defined in the Product Description
  4. Senior Supplier

Question 43

Which is an objective of the 'managing product delivery' process?

  1. To authorize the work package allocated to the team
  2. To raise exception reports when tolerance is exceeded
  3. To ensure that delivered products match expectations
  4. To record any lessons to help later management stages

Question 44

What process aims to ensure accurate progress information is provided to the Project Manager?

  1. Starting up a Project
  2. Managing a Stage Boundary
  3. Managing Product Delivery
  4. Directing a Project

Question 45

Which process covers the work done by external suppliers who may NOT be using PRINCE2?

  1. Closing a Project
  2. Managing a Stage Boundary
  3. Managing Product Delivery
  4. Directing a Project