Question 36

Which is an objective of the Initiating a Project process?

  1. Develop the corporate quality management system as part of the Project Initiation Documentation
  2. Prepare the plans for the subsequent stages
  3. Summarize how the organization's project management method will be tailored for the project
  4. Request authority from corporate management to deliver the project

Question 37

Which is NOT a purpose of the Initiating a Project process?

  1. Enable a Project Board decision about the commitment of resources to a project
  2. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
  3. Establish solid foundations for a project
  4. Enable the Project Board to decide whether it is worthwhile to initiate a project

Question 38

Which plan provides the Business Case with costs during the Initiating a Project process?

  1. Initiation Stage Plan
  2. Project Plan
  3. Stage Plan
  4. Team Plan

Question 39

Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

  1. Project Brief
  2. Project Initiation Documentation
  3. Project mandate
  4. Benefits Review Plan

Question 40

Which is a purpose of the Initiating a Project process?

  1. Decide if it is worthwhile to initiate a project
  2. Decide on the project approach
  3. Establish solid foundations for a project
  4. Identify the number of Work Packages required