Question 36
Which is an objective of the Initiating a Project process?
- Develop the corporate quality management system as part of the Project Initiation Documentation
- Prepare the plans for the subsequent stages
- Summarize how the organization's project management method will be tailored for the project
- Request authority from corporate management to deliver the project
Question 37
Which is NOT a purpose of the Initiating a Project process?
- Enable a Project Board decision about the commitment of resources to a project
- Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
- Establish solid foundations for a project
- Enable the Project Board to decide whether it is worthwhile to initiate a project
Question 38
Which plan provides the Business Case with costs during the Initiating a Project process?
- Initiation Stage Plan
- Project Plan
- Stage Plan
- Team Plan
Question 39
Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?
- Project Brief
- Project Initiation Documentation
- Project mandate
- Benefits Review Plan
Question 40
Which is a purpose of the Initiating a Project process?
- Decide if it is worthwhile to initiate a project
- Decide on the project approach
- Establish solid foundations for a project
- Identify the number of Work Packages required