Question 31

Which is an objective of the Directing a Project process?

  1. Create and authorize the project mandate
  2. Provide management control and direction
  3. Control the day-to-day running of the project
  4. Provide accurate progress information to the Project Manager

Question 32

In what process is the authorization to deliver the project's products given?

  1. Starting up a Project
  2. Initiating a Project
  3. Managing a Stage Boundary
  4. Directing a Project

Question 33

Who should act as the communication channel between a project and corporate or programme management?

  1. Project Board
  2. Project Assurance
  3. Project Manager
  4. Project Support

Question 34

Which statement about the Directing a Project process is true?

  1. Provides a mechanism for the Project Board to assure that there is continued business justification
  2. Covers the day-to-day activities of the Project Manager
  3. Ensures there are regular progress meetings
  4. Begins on completion of the Initiating a Project process

Question 35

Which of the following statements about the Project Initiation Documentation are true? 1. The Project Initiation Documentation is used to ensure that a sound basis exists before the Project Board authorizes a project. 2. The Project Initiation Documentation should be updated at the end of each stage to reflect the current status of a project.

  1. Only 1 is true
  2. Only 2 is true
  3. Both 1 and 2 are true
  4. Neither 1 or 2 are true