Question 46
Which two roles are linked by the Managing Product Delivery process?
Corporate or programme management and Project Board
Project Board and Project Manager
Project Manager and Team Manager
Team Manager and external supplier
Question 47
What is the collective name for individuals or groups who may be affected by a project?
Customers
Project Support
Stakeholders
Team members
Question 48
Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?
Create a separate Project Board to manage the supplier elements of the project
Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.
Create user and supplier groups
Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board
Question 49
When should the Project Board refer to corporate or programme management for a decision?
The stage requires resources
It is forecast that project level tolerance will be exceeded
The Senior Supplier or Senior User needs to be changed
Any request for change needs to be approved
Question 50
Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.