Question 51
Which is NOT a purpose of the Organization theme?
Define a project management team structure
Define the level of tolerance for each level of the project management team
Define the Project Board's responsibility for directing the project
Define which role is accountable for the project's success
Question 52
Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?
Those with a financial interest in the project
Those who will manage the project on a day-to-day basis
Those who will specify the desired outputs of the project
Those who will create the project's outputs
Question 53
Which does the Executive need to ensure is in place before the project is initiated?
All Work Packages are authorized
An understanding of how the project will contribute to corporate objectives
The Project Plan has been approved
The Project Initiation Documentation is complete
Question 54
Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?
Executive
Senior User
Senior Supplier
Project Manager
Question 55
What product is used to maintain a record of those who have an interest in the project and their information requirements?