Question 51

Which is NOT a purpose of the Organization theme?

  1. Define a project management team structure
  2. Define the level of tolerance for each level of the project management team
  3. Define the Project Board's responsibility for directing the project
  4. Define which role is accountable for the project's success

Question 52

Which is NOT represented by one of the three primary categories of stakeholder identified in PRINCE2?

  1. Those with a financial interest in the project
  2. Those who will manage the project on a day-to-day basis
  3. Those who will specify the desired outputs of the project
  4. Those who will create the project's outputs

Question 53

Which does the Executive need to ensure is in place before the project is initiated?

  1. All Work Packages are authorized
  2. An understanding of how the project will contribute to corporate objectives
  3. The Project Plan has been approved
  4. The Project Initiation Documentation is complete

Question 54

Which project management team member represents the interest of those who will operate the project's products to realize the benefits after the project is complete?

  1. Executive
  2. Senior User
  3. Senior Supplier
  4. Project Manager

Question 55

What product is used to maintain a record of those who have an interest in the project and their information requirements?

  1. Project Plan
  2. Communication Management Strategy
  3. Project Brief
  4. Project Product Description