Question 16

Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?

  1. Capture
  2. Examine
  3. Propose
  4. Decide

Question 17

A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?

  1. Raise a request for change
  2. Raise an off-specification
  3. Write an Exception Report
  4. Amend the Work Package

Question 18

Which of the following statements about the Closing a Project process are true? 1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage. 2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.

  1. Only 1 is true
  2. Only 2 is true
  3. Both 1 and 2 are true
  4. Neither 1 or 2 are true

Question 19

What takes place during the Closing a Project process?

  1. The post-project benefits reviews are performed
  2. Ownership of the project's products is transferred to the customer
  3. An End Stage Report is prepared for the final stage
  4. The project closure notification is reviewed and approved

Question 20

Which is an objective of the Closing a Project process?

  1. Prepare the plan for the next stage
  2. Assess any benefits that have already been realized
  3. Produce a Benefits Review Plan to identify what benefits are expected
  4. Check that all benefits are realized before closing a project