Question 16
Which step in the issue and change control procedure considers alternative options for responding to an issue that is being managed formally?
Capture
Examine
Propose
Decide
Question 17
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?
Raise a request for change
Raise an off-specification
Write an Exception Report
Amend the Work Package
Question 18
Which of the following statements about the Closing a Project process are true? 1. The Closing a Project process provides a fixed point for the receipt of completed Work Packages for the work performed in the final stage. 2. The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved.
Only 1 is true
Only 2 is true
Both 1 and 2 are true
Neither 1 or 2 are true
Question 19
What takes place during the Closing a Project process?
The post-project benefits reviews are performed
Ownership of the project's products is transferred to the customer
An End Stage Report is prepared for the final stage
The project closure notification is reviewed and approved
Question 20
Which is an objective of the Closing a Project process?
Prepare the plan for the next stage
Assess any benefits that have already been realized
Produce a Benefits Review Plan to identify what benefits are expected
Check that all benefits are realized before closing a project