Question 21
Which is a purpose of the Closing a Project process?
- Authorize the final stage of the project
- Confirm that all benefits defined in the Business Case have been achieved
- Recognize whether objectives set out in the original Project Initiation Documentation have been achieved
- Delegate day-to-day management of the end of the project to the Project Manager
Question 22
Which should be used to document any uncompleted work that needs to be done to a project product after the project has closed?
- Off-specifications
- Follow-on action recommendations
- Issue Register
- Risk Register
Question 23
Which is an objective of the 'closing a project' process?
- To provide corporate management with an interface to the project
- To ensure the project's delivery will be within set tolerances
- To seek approval to replace the project or stage plan
- To assess the benefits that have already been realized
Question 24
Which is a purpose of the Controlling a Stage process?
- Produce a Team Plan for the work to be assigned to a Team Manager
- Select and implement actions that will resolve deviations from a plan within tolerance
- Obtain approvals for products delivered in a Work Package
- Update a Project Plan to incorporate the actuals from a Stage Plan
Question 25
What process ensures focus on the delivery of a stage's products and avoids uncontrolled change?
- Directing a Project
- Managing a Stage Boundary
- Controlling a Stage
- Starting up a Project