Question 11
Which should be funded by a change budget?
- Increase in agreed scope
- Initiation stage
- Change Authority
- Handover activities
Question 12
Which should be funded from a change budget?
- The Starting up a Project process
- A fallback plan
- An agreed change to the scope of a project
- A change to a plan, within allocated tolerances, due to poor estimating
Question 13
Which is the Issue Register NOT used for?
- Capture external events that are impacting a stage
- Record information about a deviation in stage tolerance
- Capture any threats or opportunities that might have an impact on a stage
- Record any problems identified when authorizing a Work Package
Question 14
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
- Checkpoint Report
- Highlight Report
- Issue Report
- Product Status Account
Question 15
Which is the purpose of the Change theme?
- To prevent change to baselined products
- To identify, assess and control any potential and approved changes to baselined products
- To establish mechanisms to monitor and compare actual achievements against those planned
- To assess and control uncertainty