Question 6
What is an off-specification?
- A new requirement
- A quality tolerance
- A type of issue
- A major risk
Question 7
Which is a type of issue?
- A lesson
- A request for change
- An Exception Report
- A risk with an estimated high impact
Question 8
Which is a typical core activity within configuration management?
- Quality assurance
- Risk management
- Verification and audit
- Progress reporting
Question 9
Which is a typical core activity within configuration management?
- Issue management
- Quality inspection
- Identification
- Preparation
Question 10
What needs to be in place to ensure effective issue and change control?
- Configuration management system
- Manage by exception
- Quality planning
- Information needs for stakeholders