Question 6

What is an off-specification?

  1. A new requirement
  2. A quality tolerance
  3. A type of issue
  4. A major risk

Question 7

Which is a type of issue?

  1. A lesson
  2. A request for change
  3. An Exception Report
  4. A risk with an estimated high impact

Question 8

Which is a typical core activity within configuration management?

  1. Quality assurance
  2. Risk management
  3. Verification and audit
  4. Progress reporting

Question 9

Which is a typical core activity within configuration management?

  1. Issue management
  2. Quality inspection
  3. Identification
  4. Preparation

Question 10

What needs to be in place to ensure effective issue and change control?

  1. Configuration management system
  2. Manage by exception
  3. Quality planning