Question 81
Which statement about stages is true?
- Management stages should be of the same duration
- The use of technical stages is mandatory
- The use of management stages is mandatory
- Management stages are driven by specialist teams
Question 82
What product defines the reporting requirements between the Project Manager and Team Manager?
- Project Brief
- Product Description
- Team Plan
- Work Package
Question 83
Whose approval is needed to replace a Stage Plan with an Exception Plan?
- Corporate or programme management
- Project Board
- Project Manager
- Team Manager
Question 84
Which is a difference between management and technical stages?
- Management stages require planning and technical stages do not
- Technical stages can overlap and management stages cannot
- Management stages deliver products and technical stages do not
- Technical stages require resources and management stages do not
Question 85
Which is a purpose of a Lessons Log?
- Note any lessons that are raised in Checkpoint Reports
- Record that corrective action is being taken
- Escalate lessons to the Project Board
- Raise improvements with Project Assurance