Question 76

Which of the following statements about lines of authority and reporting are true? 1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board. 2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.

  1. Only 1 is true
  2. Only 2 is true
  3. Both 1 and 2 are true
  4. Neither 1 or 2 are true

Question 77

What theme provides all management levels within the project management team with mechanisms for monitoring and control?

  1. Progress
  2. Change
  3. Organization
  4. Quality

Question 78

Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?

  1. Corporate group
  2. Project Board
  3. Project Assurance
  4. Executive

Question 79

Which is a FALSE statement about technical stages?

  1. Can overlap with other technical stages
  2. Typified by the use a particular set of specialist skills
  3. Include the Managing a Stage Boundary process activities
  4. Can span more than one management stage

Question 80

How should the Team Manager report that tolerances are forecast to be exceeded?

  1. Create an Exception Report
  2. Create a Highlight Report
  3. Raise an issue
  4. Grant a concession