Question 76
Which of the following statements about lines of authority and reporting are true? 1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board. 2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
Only 1 is true
Only 2 is true
Both 1 and 2 are true
Neither 1 or 2 are true
Question 77
What theme provides all management levels within the project management team with mechanisms for monitoring and control?
Progress
Change
Organization
Quality
Question 78
Who should use the information in a Lessons Report to refine, change and improve the standards within a quality management system?
Corporate group
Project Board
Project Assurance
Executive
Question 79
Which is a FALSE statement about technical stages?
Can overlap with other technical stages
Typified by the use a particular set of specialist skills
Include the Managing a Stage Boundary process activities
Can span more than one management stage
Question 80
How should the Team Manager report that tolerances are forecast to be exceeded?