Question 71

Which characteristic of a project reflects that there are different perspectives and motivations for customers and suppliers?

  1. Change
  2. Cross-functional
  3. Unique
  4. Risk

Question 72

Which PRINCE2 principle is supported by the setting of tolerances for the three levels of plan?

  1. Manage by stages
  2. Manage by exception
  3. Continued business justification
  4. Learn from experience

Question 73

Which role is responsible for creating Checkpoint Reports?

  1. Senior Supplier
  2. Team Manager
  3. Change Authority
  4. Project Support

Question 74

Identify the missing words in the following sentence. A Project Manager agrees the [ ? ] with a Team Manager.

  1. project cost tolerance
  2. stage cost tolerance
  3. Work Package cost tolerance
  4. product cost tolerance

Question 75

Which is a true statement about time-driven controls?

  1. Time-driven controls are used for monitoring the progress of Work Packages and management stages
  2. Time-driven controls take place when specific events happen
  3. Time-driven controls are produced at the end of a stage
  4. An Exception Report is a time-driven control