Question 66
Which is a benefit of using PRINCE2?
- Enables the management of projects as well as of 'business as usual' activities
- Can be tailored by leaving out elements of the method for some projects
- Can be applied to any type of project
- Avoids the need to involve corporate or programme management
Question 67
Which is a benefit of using PRINCE2?
- Is a method specifically designed for technical projects
- Provides for the efficient and economic use of management time
- Includes many of the proven planning techniques, such as critical path analysis
- Can be used to manage both projects and programmes
Question 68
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?
- Specify the desired result
- Provide the resources and skills to deliver the desired result
- Pay for the project
- Specify the benefits of the project
Question 69
Which does NOT reflect the PRINCE2 principle of continued business justification?
- There must be a justifiable reason for starting a project
- The business justification drives decision making
- If a project is no longer forecast to deliver a financial benefit, it should be stopped.
- If a project can no longer be justified, it should be stopped
Question 70
Which characteristic distinguishes a project from regular business operations?
- Produces benefits
- Introduces business change
- Manages stakeholders
- Incurs cost