Question 66

Which is a benefit of using PRINCE2?

  1. Enables the management of projects as well as of 'business as usual' activities
  2. Can be tailored by leaving out elements of the method for some projects
  3. Can be applied to any type of project
  4. Avoids the need to involve corporate or programme management

Question 67

Which is a benefit of using PRINCE2?

  1. Is a method specifically designed for technical projects
  2. Provides for the efficient and economic use of management time
  3. Includes many of the proven planning techniques, such as critical path analysis
  4. Can be used to manage both projects and programmes

Question 68

Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?

  1. Specify the desired result
  2. Provide the resources and skills to deliver the desired result
  3. Pay for the project
  4. Specify the benefits of the project

Question 69

Which does NOT reflect the PRINCE2 principle of continued business justification?

  1. There must be a justifiable reason for starting a project
  2. The business justification drives decision making
  3. If a project is no longer forecast to deliver a financial benefit, it should be stopped.
  4. If a project can no longer be justified, it should be stopped

Question 70

Which characteristic distinguishes a project from regular business operations?

  1. Produces benefits
  2. Introduces business change
  3. Manages stakeholders
  4. Incurs cost