Question 61
Which is NOT included in the PRINCE2 definition of a project?
A project is a temporary organization
A project's purpose is to deliver one or more business products
A project is part of 'business as usual'
A project is based on an agreed Business Case
Question 62
Identify the missing words in the following sentence. A project is [ ? ] organization that is created for the purpose of delivering business products.
a corporate
a temporary
an external
a technical
Question 63
Identify the missing word in the following sentence. The guiding obligations and good practices which determine whether the project is genuinely being managed using PRINCE2 form the [ ? ] of the method.
Principles
Themes
Processes
Techniques
Question 64
Which is NOT one of the PRINCE2 integrated elements?
Tailoring PRINCE2 to the project environment
The processes
The products
The themes
Question 65
Which is assumed to be a customer's responsibility in the PRINCE2 customer/supplier environment?
Specify the desired result
Provide the resources and skills to deliver the desired result