Question 86

Which is a true statement about PRINCE2 event-driven controls?

  1. Event-driven controls take place at predefined periodic intervals
  2. Event-driven controls are produced at the frequency defined in a Work Package
  3. Event-driven controls are used for decision making
  4. Checkpoint Reports are event-driven controls

Question 87

Which is a purpose of an End Project Report?

  1. Identify individuals or groups that need to be told that the project is coming to an end
  2. Review how well the project performed against the Project Initiation Documentation used to authorize it
  3. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
  4. Ensure that key project information is archived and made secure

Question 88

How many management stages should a PRINCE2 project consist of?

  1. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
  2. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
  3. Initiation stage and at least one other management stage to cover the remainder of the project
  4. Start up stage, initiation stage and a closing stage

Question 89

What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?

  1. Configuration Item Record
  2. Quality Register
  3. Highlight Report
  4. Checkpoint Report

Question 90

Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

  1. Only corporate or programme management
  2. Only the Project Board
  3. Only the Project Manager
  4. All levels of management