Question 86
Which is a true statement about PRINCE2 event-driven controls?
- Event-driven controls take place at predefined periodic intervals
- Event-driven controls are produced at the frequency defined in a Work Package
- Event-driven controls are used for decision making
- Checkpoint Reports are event-driven controls
Question 87
Which is a purpose of an End Project Report?
- Identify individuals or groups that need to be told that the project is coming to an end
- Review how well the project performed against the Project Initiation Documentation used to authorize it
- Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
- Ensure that key project information is archived and made secure
Question 88
How many management stages should a PRINCE2 project consist of?
- Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
- Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
- Initiation stage and at least one other management stage to cover the remainder of the project
- Start up stage, initiation stage and a closing stage
Question 89
What product would enable the Project Manager to review how a Work Package is performing against its cost tolerance?
- Configuration Item Record
- Quality Register
- Highlight Report
- Checkpoint Report
Question 90
Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?
- Only corporate or programme management
- Only the Project Board
- Only the Project Manager
- All levels of management