Question 21
Which statement explains the target 'be on time and hit deadlines' for flexible delivery?
- It reduces testing in order to meet deadlines
- It sets the project baseline at the correct level
- It enables team dynamics to remain the same
- It improves the supplier's reputation with the customer
Question 22
Which statement about the 'protect the level of quality' target is CORRECT?
- It is achieved by allowing enough time for testing
- It is achieved by using the same team members
- It gives confidence on the progress of the project
- It delivers the early realization of benefits
Question 23
Which statement describes the Kanban approach?
- It is used to make system improvements using visualization and by controlling work in progress
- It is an iterative timeboxed approach that helps teams generate value
- It was originally focused in creating new companies and is now used to speed up product delivery
- It has defined processes, products and roles used to iteratively deliver outputs using timeboxing
Question 24
What information is NOT typically displayed on a burn chart?
- Effort remaining
- Definition of 'ready'
- Actual amount of work done
- Amount of time elapsed
Question 25
In which area is Agile strongest when blending with PRINCE2?
- Product delivery
- Project management
- Project direction
- Product management