PRINCE2 Agile Foundation Practice Test

PRINCE2 Agile Foundation Practice Test practice questions, page 5 of 7, with answer review and explanations.

Question 21

Which statement explains the target 'be on time and hit deadlines' for flexible delivery?

  1. It reduces testing in order to meet deadlines
  2. It sets the project baseline at the correct level
  3. It enables team dynamics to remain the same
  4. It improves the supplier's reputation with the customer

Question 22

Which statement about the 'protect the level of quality' target is CORRECT?

  1. It is achieved by allowing enough time for testing
  2. It is achieved by using the same team members
  3. It gives confidence on the progress of the project
  4. It delivers the early realization of benefits

Question 23

Which statement describes the Kanban approach?

  1. It is used to make system improvements using visualization and by controlling work in progress
  2. It is an iterative timeboxed approach that helps teams generate value
  3. It was originally focused in creating new companies and is now used to speed up product delivery
  4. It has defined processes, products and roles used to iteratively deliver outputs using timeboxing

Question 24

What information is NOT typically displayed on a burn chart?

  1. Effort remaining
  2. Definition of 'ready'
  3. Actual amount of work done
  4. Amount of time elapsed

Question 25

In which area is Agile strongest when blending with PRINCE2?

  1. Product delivery
  2. Project management
  3. Project direction
  4. Product management