Question 16
What needs to happen when new detailed requirements are added to a timebox?
- Requirements of a similar level of effort should be removed
- More people should be added to the delivery team
- The delivery milestones should be reviewed and re-planned
- Formal change control should be applied
Question 17
Which statement about the 'accept that the customer doesn't need everything' target is correct?
- It gives confidence on the progress of the project
- It can result in the early delivery of a minimum viable product
- It allows misunderstandings to be dealt with appropriately
- It is achieved by managing the culture of the team carefully
Question 18
Which statement about velocity is CORRECT?
- It is based on the concept of rationalism
- It is shown by the ideal line on a bum-down chart
- It describes how much work is getting done
- It tracks the time and cost of a timebox
Question 19
Which is a purpose of the 'controlling stage' process?
- To execute and deliver the project product
- To establish whether the project is complete
- To report stage progress to the project board
- To draft the plan for the next stage's work
Question 20
Which is a typical characteristic of 'business as usual' work?
- It requires a specific dedicated project manager
- It is executed by program management
- It is delivered by a temporary team
- It is delivered by an established team