Question 26
Which role is responsible for facilitating the Agilometer assessment?
- Project board
- Project manager
- Team manager
- Customer subject matter expert
Question 27
What is an epic?
- A detailed user story with high business value
- The set of products handed over to the users
- A high-level user story that is quite broad or vague
- A prioritized list of requirements to be delivered in a sprint
Question 28
Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?
- To use empiricism, based on knowledge that comes from experience
- To build, measure, learn from your experiences
- To create a minimum viable product to manage uncertainty
- To fail fast, if you are going to fail
Question 29
Which statement explains the setting of the cost tolerance for a project in an agile context?
- Cost tolerance is flexed
- Cost tolerance can be fixed or flexed
- Cost tolerance can be fixed and flexed
- Cost tolerance is fixed
Question 30
In Scrum, what answers the question 'what can be done this sprint?'
- Daily scrum
- Sprint review
- Sprint planning