Question 26

Which role is responsible for facilitating the Agilometer assessment?

  1. Project board
  2. Project manager
  3. Team manager
  4. Customer subject matter expert

Question 27

What is an epic?

  1. A detailed user story with high business value
  2. The set of products handed over to the users
  3. A high-level user story that is quite broad or vague
  4. A prioritized list of requirements to be delivered in a sprint

Question 28

Which is NOT one of the core concepts of Lean Startup that apply to PRINCE2?

  1. To use empiricism, based on knowledge that comes from experience
  2. To build, measure, learn from your experiences
  3. To create a minimum viable product to manage uncertainty
  4. To fail fast, if you are going to fail

Question 29

Which statement explains the setting of the cost tolerance for a project in an agile context?

  1. Cost tolerance is flexed
  2. Cost tolerance can be fixed or flexed
  3. Cost tolerance can be fixed and flexed
  4. Cost tolerance is fixed

Question 30

In Scrum, what answers the question 'what can be done this sprint?'

  1. Daily scrum
  2. Sprint review
  3. Sprint planning
  4. Increment