Question 91
During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting.What should the project manager do?
Call for a change control board (CCB) meeting, and inform the stakeholder about the outcome
Update the communications management plan and implement the change
Meet with the project sponsor to discuss how to address the situation
Meet with the stakeholder prior to the meeting to obtain their opinion
Question 92
The project manager started a new project and must ensure that the team members and stakeholders are adequately trained. After an interview with the team, the project manager discovers that all resources have experience in different agile methodologies.What should the project manager do?
Make sure the project team is aware of all agile techniques
Skip the training because the team already understands agile
Ensure the team has a common understanding of agile
Teach one agile methodology fully and completely
Question 93
A project manager is assigned to a new project to deliver a product at the end of the year. The project manager was informed by the vendor that a core component could not be shipped on time, which will impact the schedule.What should project manager to do next to minimize the impact on the project?
Schedule a meeting with all stakeholders to extend the project deadline
Replace the vendor with a new vendor who can offer the component on time
Add an item to the next status review to make stakeholders aware of the vendor issue
Review and update the issue log and determine if any alternative components can be offered
Question 94
A project to develop a large hydropower plant is in the implementation phase and is managed using a hybrid approach.What should the project manager do to ensure full compliance of quality requirements during the execution phase?
Analyze the quality requirements.
Plan quality management
Continually survey the quality of the deliverable
Set up quality policies and procedures
Question 95
As part of the strategic plan, a company decides to implement a new software platform to manage a centralized document repository. Some requirements are clear and some need more detail.What should the project manager do first to decide how to manage this project?
Select a predictive development life cycle based on the team's experience
Determine the most appropriate life cycle approach for the project
Register all requirements into a backlog for further detailed analysis
Split the requirements, put them into two separate projects, and apply different approaches