Question 86
An agile team member from a cross-functional team has been unable to complete assignments due to tasks assigned by the functional manager. What should the scrum master do?
Dismiss the team member
Discuss the situation with the functional manager
Report the functional manager to the project sponsor
Demand that the functional manager respect the project charter
Question 87
During a mature agile team's planning meeting, a team member proposes a new framework that would considerably reduce implementation time. However, the team lacks the confidence to try the new framework. To help the team gain confidence, what should the agile practitioner suggest?
Develop a spike
Create an Ishikawa diagram
Perform a pre-mortem analysis
Complete a variance and trend analysis
Question 88
The team is in the middle of an iteration and there is an urgent request for a small change to be introduced to the committed scope. Unless this change is accepted, there is no value to the customers during this iteration. What must the agile practitioner do?
Add the new change request as a new user story in the product backlog for the upcoming iteration
Evaluate the impact of the change request and let the team and product owner decide and re-prioritize based on value
Recommend cancelling the current iteration and plan the change request into the next iteration
Recommend that the product owner add this change request as a user story to the backlog for the current iteration
Question 89
During a review session, an agile team presented done requirements to a group of stakeholders. Stakeholder feedback indicated that the done requirements failed to meet most pressing needs and provide value. What should the team have done to prevent this?
Reprioritized requirements prior to committing to iteration work
Ensured that requirements remained stable during the iteration cycle
Had stakeholders focus on items created after the product backlog was initially built
Worked on features rather than a set of components
Question 90
A member of a project's development team approaches the team lead and requests database administrator training. The team member believes that their inability to handle this work and to rely on outside specialists is impacting team velocity. What should the agile team lead do?
Send the member to training
Ask the outside specialists if database administration is required from the team
Send one member to training only after asking the team if there is an issue with the current work flow
Wait until all members of the team can attend training