PMI-ACP Practice Test practice questions, page 17 of 20, with answer review and explanations.
Question 81
During a sprint review, the product owner identifies a required improvement for a feature's user interface (UI) delivered during the sprint. What should the product owner do next?
Create a user story for this new improvement and put it in the product backlog for prioritization and validation by the customer
Create a user story for this new improvement and prioritize it for the next sprint
Document it as a requirement creep
Ask the team to take on additional story points to improve the UI
Question 82
A company is moving into a new space and is determining the best configuration for offices. The management team is also considering moving to an agile process. What should an agilest give?
Arrange the office space to allow co-location of development teams and centrally located information radiators
Isolate each development team to reduce all outside distractions
Ensure management understands the need for isolation to allow for concentration
Define the agile method the company will be using and implement the office configuration based upon that method
Question 83
An agile team member identifies a potential problem within the project team. How should the team's coach react?
Document the problem, escalate to the project manager, and develop a solution for the team
Add the problem to the backlog and assign resolution to a future iteration
Instruct the team to try to solve the problem within the team
Perform root cause analysis and report the problem to the product owner
Question 84
Stakeholders are displeased with the latest release of a product's software. While most stakeholders attended every sprint review, they were otherwise largely uninvolved in the project. What should the agile practitioner have done to ensure stakeholder satisfaction?
Communicated early and often, as outlined in the communications matrix
Ensured engagement among stakeholders and the product owner
Conducted additional stakeholder reviews and demos
Worked with the product owner to prioritize user stories
Question 85
An agile project manager notices that the product manager manages team member's day-to-day tasks in a way that distracts them from their core responsibilities. In addition, the team believes that their questions on product backlog prioritization are not being answered on time. What should the agile practitioner do?
Discuss and address this in the iteration retrospective
Let the product owner know it is the project manager's responsibility to drive a ream's tasks
Discuss the roles and responsibilities of the project team with the product owner
Ask the product owner to work extra hours to answer the team's questions