Question 71

While reviewing the sprint burn down during a stand up, the scrum team identifies that they have fallen behind. Upon further discussion, they discover that some quality assurance (QA) team members were unable to use the new automation framework, which caused a bottleneck. What should the scrum team do?

  1. For upcoming sprints, have QA team members ensure that their respective skill sets are considered when accepting stories
  2. Have QA team members with the appropriate skill sets spend extra to help the team succeed
  3. Ensure that QA team members who lack the appropriate skill up for training within the next few weeks
  4. Ask QA team members experienced with the new automation framework to cross-train the other QA members

Question 72

An organization highly values security. However, a team member on a project has found a way to save time and money with less robust security features. What should the team member do?

  1. Influence the customer
  2. Mention the idea at the next retrospective
  3. Show the customer how much time and money would be saved
  4. Present the idea at the next ceremony attended by stakeholders to obtain their input

Question 73

During its first sprint, a new scrum team realizes that it has insufficient team members with test automation skills to efficiently complete its stories. What should the team do?

  1. Cross-train some members in the automation framework to broaden their capacity with that skill
  2. Ask the product owner to add team members to boost this particular skill set
  3. Send a member to automation framework training when funds are available
  4. Avoid using test automation by swarming on the testing tasks and using manual testing

Question 74

During sprint planning, team members have differing opinions on a feature that delivers business value but fails to provide a long-term solution for the customer. How should the team resolve this?

  1. Refer to the values of the agile framework and the team
  2. Review the signed customer contract
  3. Check the sprint priority list
  4. Submit the problem to the product owner

Question 75

A project team realizes that an important task on the iteration backlog will take more time than originally estimated. What should the project team do?

  1. Continue working on the task until it is completed
  2. Remove the task owner from the project team
  3. Add resources to reduce time to task completion
  4. Stop working on the task and include it in the next iteration