PK0-005 Practice Test practice questions, page 16 of 25, with answer review and explanations.
Question 76
For an upcoming project kickoff, a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?
Resource plan
Organizational chart
Project charter
RACI chart
Question 77
Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?
Kanban board
Pareto chart
Ishikawa diagram
Decision tree
Question 78
A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?
Dashboard
Gantt chart
Work breakdown structure
Requirements Traceability Matrix
Question 79
When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?
Critical paths
Resources
Milestones
Work breakdown structures
Question 80
A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?
Decline because it is not included in the project scope.
Assess the impact of the request and create a change request.
Create new functional and non-functional requirements for mobile devices.
Revise the baseline of the project plan by adding the new requirements.