Question 76

For an upcoming project kickoff, a PM is looking for a way to illustrate roles for major project activities. Which of the following would be the MOST useful option?

  1. Resource plan
  2. Organizational chart
  3. Project charter
  4. RACI chart

Question 77

Defects associated with project deliverables have been reported. The project team needs to find the cause of the defects. Which of the following tools should the project team use to find the cause?

  1. Kanban board
  2. Pareto chart
  3. Ishikawa diagram
  4. Decision tree

Question 78

A project manager needs to update the project sponsor and senior stakeholders about the progress of a project. Which of the following tools will the project manager MOST likely use?

  1. Dashboard
  2. Gantt chart
  3. Work breakdown structure
  4. Requirements Traceability Matrix

Question 79

When creating a project schedule, a project manager adds activities with zero duration. Which of the following describes these types of activities?

  1. Critical paths
  2. Resources
  3. Milestones
  4. Work breakdown structures

Question 80

A project manager reports that the implementation of a new system is on track to be completed under budget and ahead of the schedule. A stakeholder then asks the manager to add mobile device functionality. Which of the following should the project manager do in response to the request?

  1. Decline because it is not included in the project scope.
  2. Assess the impact of the request and create a change request.
  3. Create new functional and non-functional requirements for mobile devices.
  4. Revise the baseline of the project plan by adding the new requirements.