Question 71

A project team has just experienced an unexpected event and implemented a work-around. Which of the following documents should be used to record the event? (Choose two.)

  1. Risk report
  2. Defect log
  3. Issue log
  4. Backlog
  5. Change log
  6. Progress report

Question 72

A project implementation partner and the project manager disagree about completed requirements. The project manager shows the project requirements as 70% complete. The implementation partner validates that all requirements were completed. Which of the following would clarify what the project implementation partner was contractually expected to complete?

  1. SOW
  2. RFI
  3. RFQ
  4. WBS

Question 73

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?

  1. Determine budget constraints.
  2. Validate the business case.
  3. Update the project charter.
  4. Create a project schedule.

Question 74

A key stakeholder recommends to a senior developer that a new feature be added. The new feature is not part of the current requirement documentation. Which of the following is MOST likely happening?

  1. Scope creep
  2. Collecting requirements
  3. Decision-making
  4. Project change

Question 75

Which of the following BEST illustrates how team members with different roles should interact on the team?

  1. SOW
  2. WBS
  3. RACI
  4. PERT