PK0-005 Practice Test

PK0-005 Practice Test practice questions, page 14 of 25, with answer review and explanations.

Question 66

Which of the following would be the NEXT document a project manager should update once the need to procure goods and/or services is identified?

  1. Memorandum of understanding
  2. Request for information
  3. Statement of work
  4. Non-disclosure agreement

Question 67

A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?

  1. Create a list of tasks and share it with the team.
  2. Resend the scope of work to the team.
  3. Review the Gantt chart weekly with the team.
  4. Have the project sponsor meet with the team.

Question 68

A project manager has been informed that the delivery of required IT equipment will be delayed. Which of the following is the FIRST step the project manager should take?

  1. Make an impact assessment.
  2. Prepare a new purchase order.
  3. Select a new vendor.
  4. Create a risk register.

Question 69

Which of the following BEST identifies the intent and purpose of a project closeout report?

  1. To provide documentation of lessons learned
  2. To document variances from the initial project baseline
  3. To validate that a project has been successfully completed
  4. To release resources and terminate all access rights

Question 70

A PM is working with stakeholders in the discovery phase and comparing the cost of the project to the cost savings the project will produce when it is complete. The output of this exercise will produce the:

  1. ROI.
  2. SOW.
  3. RFI.
  4. RFP.