PK0-005 Practice Test practice questions, page 13 of 25, with answer review and explanations.
Question 61
While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM’s time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?
Perform a root cause analysis.
Organize a stakeholder meeting.
Escalate the issue to the CCB.
Contact the PMO for assistance.
Question 62
A financial manager reports that several employees’ allocations from the past month appear to be 200% even though they are only assigned to a particular project. Which of the following could MOST likely be the cause of this issue?
A project manager assigned the wrong resources.
A project manager did not release the resources.
A project manager did not remove the system access.
A project manager did not provide the project sign-off.
Question 63
Which of the following requires the MOST availability from the business team?
SDLC
Scrum
PRINCE2
Waterfall
Question 64
Which of the following software programs would be BEST to use to store information related to business transactions?
Record management system
Customer relationship management
Enterprise resource planning
Content management system
Question 65
During a status meeting, the development team reviews work and finds an unforeseen dependency on one of the critical project activities. As a result, the project will most likely be delayed. Which of the following actions should the project manager MOST likely perform?
Work with the project scheduler to update the project timeline.
Communicate to the stakeholders about the updated timeline.
Ask the development team to fast-track upcoming activities.
Add two resources so the critical activities will finish on time.