PK0-005 Practice Test practice questions, page 17 of 25, with answer review and explanations.
Question 81
During a code implementation, a senior developer and junior tester are discussing the testing scenarios that were performed. A major malfunction resulted in an inoperative product condition. As a result, the team was forced to work until midnight to restore operations. Which of the following should the PM have generated FIRST to alleviate the impact of this issue prior to deployment?
A risk budget
A risk impact
A change request
A contingency plan
Question 82
During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?
Procurement
Communication
Quality assurance
Risk
Question 83
A PM learns about some communication issues with different stakeholders and team members. Which of the following should the PM do NEXT?
Escalate the communication issues.
Implement a communication platform.
Review the communication plan.
Talk with the head of the PMO.
Question 84
An organization was fined due to an audit finding that revealed a third-party vendor was able to see secured project information in a recently implemented system. Which of the following was the cause of this situation?
The ticket system provided access by default without any approval.
The project manager did not perform proper project planning.
The system is lacking proper access controls.
Sensitive data was incorrectly classified during the audit process.
Question 85
An institution wants to implement software solutions to help manage the internal flow for formally responding in writing to citizens’ complaints. Which of the following solutions would be BEST?
Enterprise resource planning and end user applications