Question 41
The Project Communications Management knowledge area focuses on which of the following processes? Each correct answer represents a complete solution. Choose all that apply.
Create Work Breakdown Structure (WBS)
Distribute Information
Report Performance
Identify Stakeholders
Question 42
In which of the following processes are the results of executing the quality activities recorded and monitored in order to assess performance and recommend necessary changes?
Plan Quality
Perform Quality Assurance
Control Cost
Perform Quality Control
Question 43
Which of the following theories describes the statement below? "It states that there are certain factors in the workplace that cause job satisfaction, while a separate set of factors cause dissatisfaction."
Herzberg's theory
Ouchi's Theory Z
McGregor's X and Y
Expectancy theory
Question 44
Which of the following techniques is described in the statement below? "It is used to verify whether a particular work can best be accomplished by the project team or must be purchased from outside sources."
Risk analysis
Expert judgment
Make-or-Buy analysis
Contract type
Question 45
Which of the following tasks are performed by the scope development process?
To facilitate clear responsibility assignments
To define a baseline for performance measurement and control
To improve the accuracy of cost, duration, and resource estimates