Question 46
You work as a project manager for BlueWell Inc. You are currently working with the project stakeholders to identify risks in your project. You understand that the qualitative risk assessment and analysis can reflect the attitude of the project team and other stakeholders to risk. Effective assessment of risk requires management of the risk attitudes of the participants. What should you, the project manager, do with assessment of identified risks in consideration of the attitude and bias of the participants towards the project risk?
Document the bias for the risk events and communicate the bias with management
Evaluate the bias through SWOT for true analysis of the risk events
Evaluate the bias towards the risk events and correct the assessment accordingly
Evaluate and document the bias towards the risk events
Question 47
You are the project manager for your organization and are planning the project work with your project team. You are currently breaking down the project scope into work packages to determine an accurate time and cost estimate. What document are you and the project team creating?
Work breakdown structure
Project scope
Code of accounts
Work breakdown dictionary
Question 48
You are a new Project Manager that has been entrusted with a software development project. You have started building the list of activities and sequencing them for your project schedule model. As part of the activities, you have identified that your project team will need to start resolving the defects that come out of the User Testing, 5 days after the testing starts. Which of the following would be the correct way to represent this logical relationship between the activities?
Start to Start Dependency, with 5 days lead.
Finish to Start Dependency
Start to Start Dependency with 5 days lag.
Finish to Finish Dependency, with constraint to start after 5 days.
Question 49
Which of the following tasks are performed by the scope development process?
To define a baseline for performance measurement and control
To improve the accuracy of cost, duration, and resource estimates
To determine whether a scope change has occurred
To facilitate clear responsibility assignments
Question 50
Which of the following quality costs determines, assesses, or audits products or services to assure conformance to quality standards and performance requirements?