Question 36

Gary has identified a project risk that could injure project team members. He does not want to accept any risk where someone could become injured on this project, so he hires a professional vendor to complete this portion of the project work. This workaround to the risk event is known as what type of risk response?

  1. Avoidance
  2. Acceptance
  3. Mitigation
  4. Transference

Question 37

Which of the following types of organizational structures represents a hierarchy where every member has one leader and the employees are grouped by the area of expertise?

  1. Projectized
  2. Jury
  3. Functional
  4. Matrix

Question 38

Which of the following are inputs of the Acquire Project Team process?

  1. Resource calendars
  2. Project management plan
  3. Enterprise environmental factors
  4. Organizational process assets

Question 39

Which of the following are outputs of the perform quality assurance process?

  1. Change requests
  2. Project management plan updates
  3. Organizational process assets update
  4. Work performance information

Question 40

You are the project manager for your organization. Your organization manages projects for other companies. You will be soon managing a project for the JUH Company. What document do you need first to help to develop the project charter?

  1. Functional requirements
  2. Preliminary project scope statement
  3. Business requirements
  4. Contract