GCPM Practice Test practice questions, page 7 of 15, with answer review and explanations.
Question 31
Which of the following forecasting methods is described in the statement below? "It is based on the assumption that it is possible to identify some factors that might influence the variable that is being forecasted."
Causal/econometric method
Judgmental method
Ensemble forecasting
Time series method
Question 32
Identify Risks is the process of determining which risks may affect the project. Which of the following are inputs of the Identify risks process?
Risk management plan
Risk register
Scope baseline
Project documents
Question 33
Which of the following forecasting methods is described in the statement below? "It is based on the assumption that it is possible to identify some factors that might influence the variable that is being forecasted."
Causal/econometric method
Judgmental method
Ensemble forecasting
Time series method
Question 34
Identify Risks is the process of determining which risks may affect the project. Which of the following are inputs of the Identify risks process?
Risk management plan
Risk register
Scope baseline
Project documents
Question 35
You work as a project manager for HRM Inc. Your project has a schedule variance of -$35,500 and a schedule performance index of 0.92. What do these values mean in regard to project performance?
The project is performing well.
The project has a planned value of $600,000.
The project is likely to be late and over budget.
The project is eight percent off schedule and has a considerable schedule variance.