Question 26
Virginia is the project manager for her organization. She has hired a subject matter expert to interview the project stakeholders on certain identified risks within the project. The subject matter expert will assess the risk event with what specific goal in mind?
To determine the validity of each risk event
To determine the level of probability and impact for each risk event
To determine the probability and schedule of the risk event
To determine the bias of the risk event based on each person interviewed
Question 27
You are the project manager of the TRT Project. During the execution phase of your project, Rick, a team member, complains that other team members are isolating him and this isolation is bothering him. Which of the following is NOT a recommended step to resolve the issue?
Get feedback on Rick from other team members.
Shift Rick to another project.
Get more feedback from Rick.
Apply team building measures to improve the team's effectiveness.
Question 28
Which of the following forecasting methods is described in the statement below? "It is based on the assumption that it is possible to identify some factors that might influence the variable that is being forecasted."
Causal/econometric method
Judgmental method
Ensemble forecasting
Time series method
Question 29
FILL BLANK - Fill in the blank with the appropriate term. _____________________(also called contractor conferences, vendor conferences, and pre-bid conferences) are meetings with prospective sellers prior to preparation of a bid or proposal.
Question 30
Identify Risks is the process of determining which risks may affect the project. Which of the following are inputs of the Identify risks process?