Question 286
Which of the following components ensures that risks are examined for all new proposed change requests in the change control system?
Configuration management
Scope change control
Risk monitoring and control
Integrated change control
Question 287
Which of the following are true for threats? Each correct answer represents a complete solution. (Choose three.)
They can become more imminent as time goes by, or it can diminish
They can result in risks from external sources
They are possibility
They are real
They will arise and stay in place until they are properly dealt.
Question 288
Which of the following statements BEST describes policy?
A minimum threshold of information security controls that must be implemented
A checklist of steps that must be completed to ensure information security
An overall statement of information security scope and direction
A technology-dependent statement of best practices
Question 289
You are the project manager of GHT project. You have analyzed the risk and applied appropriate controls. In turn, you got residual risk as a result of this. Residual risk can be used to determine which of the following?
Status of enterprise's risk
Appropriate controls to be applied next
The area that requires more control
Whether the benefits of such controls outweigh the costs
Question 290
When it appears that a project risk is going to happen, what is this term called?