Question 281
You work as a Project Manager for Company Inc. You have to conduct the risk management activities for a project. Which of the following inputs will you use in the plan risk management process? Each correct answer represents a complete solution. (Choose three.)
Quality management plan
Schedule management plan
Cost management plan
Project scope statement
Question 282
Which of the following documents is described in the statement below? "It is developed along with all processes of the risk management. It contains the results of the qualitative risk analysis, quantitative risk analysis, and risk response planning."
Quality management plan
Risk management plan
Risk register
Project charter
Question 283
You have identified several risks in your project. You have opted for risk mitigation in order to respond to identified risk. Which of the following ensures that risk mitigation method that you have chosen is effective?
Reduction in the frequency of a threat
Minimization of inherent risk
Reduction in the impact of a threat
Minimization of residual risk
Question 284
Which of the following control is used to ensure that users have the rights and permissions they need to perform their jobs, and no more?
System and Communications protection control
Audit and Accountability control
Access control
Identification and Authentication control
Question 285
You are working in an enterprise. Your enterprise owned various risks. Which among the following is MOST likely to own the risk to an information system that supports a critical business process?