Question 291

You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. Which of the following inputs will be needed for the qualitative risk analysis process in your project? Each correct answer represents a complete solution. (Choose three.)

  1. Project scope statement
  2. Cost management plan
  3. Risk register
  4. Organizational process assets

Question 292

Which of the following will significantly affect the standard information security governance model?

  1. Currency with changing legislative requirements
  2. Number of employees
  3. Complexity of the organizational structure
  4. Cultural differences between physical locations

Question 293

You are the risk professional in Bluewell Inc. You have identified a risk and want to implement a specific risk mitigation activity. What you should PRIMARILY utilize?

  1. Vulnerability assessment report
  2. Business case
  3. Technical evaluation report
  4. Budgetary requirements

Question 294

You are the project manager of the AFD project for your company. You are working with the project team to reassess existing risk events and to identify risk events that have not happened and whose relevancy to the project has passed. What should you do with these events that have not happened and would not happen now in the project?

  1. Add the risk to the issues log
  2. Close the outdated risks
  3. Add the risks to the risk register
  4. Add the risks to a low-priority watch-list

Question 295

What activity should be done for effective post-implementation reviews during the project?

  1. Establish the business measurements up front
  2. Allow a sufficient number of business cycles to be executed in the new system
  3. Identify the information collected during each stage of the project