Question 291
You work as a project manager for SoftTech Inc. You are working with the project stakeholders to begin the qualitative risk analysis process. Which of the following inputs will be needed for the qualitative risk analysis process in your project? Each correct answer represents a complete solution. (Choose three.)
Project scope statement
Cost management plan
Risk register
Organizational process assets
Question 292
Which of the following will significantly affect the standard information security governance model?
Currency with changing legislative requirements
Number of employees
Complexity of the organizational structure
Cultural differences between physical locations
Question 293
You are the risk professional in Bluewell Inc. You have identified a risk and want to implement a specific risk mitigation activity. What you should PRIMARILY utilize?
Vulnerability assessment report
Business case
Technical evaluation report
Budgetary requirements
Question 294
You are the project manager of the AFD project for your company. You are working with the project team to reassess existing risk events and to identify risk events that have not happened and whose relevancy to the project has passed. What should you do with these events that have not happened and would not happen now in the project?
Add the risk to the issues log
Close the outdated risks
Add the risks to the risk register
Add the risks to a low-priority watch-list
Question 295
What activity should be done for effective post-implementation reviews during the project?
Establish the business measurements up front
Allow a sufficient number of business cycles to be executed in the new system
Identify the information collected during each stage of the project