CMM: Certified Construction Manager practice questions, page 3 of 7, with answer review and explanations.
Question 11
Halfway through construction, the CM notices a cost variance. Material costs are 20% higher than expected at this point. Which of the following is the BEST initial response?
Revise the budget.
Meet with the owner to revise the budget.
Terminate the prime builder for not meeting design specifications.
Analyze relevant schedule and risk data to identify the root cause.
Question 12
At what phase does the program manager have the BEST opportunity for improving the chances for success?
Design
Construction
Program development
Project definition
Question 13
At what stage of the design phase shall the CM conduct a constructability review?
90% design stage
60% design stage
30% design stage
Throughout the design process including 100% design documents
Question 14
At the owner’s rep, you are providing on-site construction management services to a municipality for their new design-build city mall project. While developing your project risk register, the owner indicated that no soil borings were done. What risk rating would you assign to this risk of unknown site conditions?
High
Medium
Low
No risk
Question 15
Lifecycle analysis of a project will provide the greatest impact during which of the following phases?