Question 31

In the typical design-bid-build delivery system, when the CM is evaluating risk for the owner during design, which of the following are the key risks to the owner?

  1. Contractor and constructability
  2. Quality and safety
  3. Cost and schedule
  4. Phasing and procurement

Answer: C. Cost and schedule

Cost and schedule are principal owner risks during DBB design.

Question 32

A CM team on a new project which is the pre-design phase is planning their climate resiliency strategy. Which of the following is the team’s BEST first step in this process?

  1. Hire a commissioning agent.
  2. Collect relevant data and reports.
  3. Establish a third-party certification.
  4. Establish QA/QC specifications.

Answer: B. Collect relevant data and reports.

Start by gathering relevant climate and site data.

Question 33

One word or phrase to describe the process of transitioning from construction to permanent operations by the owner is

  1. turnover.
  2. O&M.
  3. beneficial occupancy.
  4. move-in.

Answer: A. turnover.

Turnover is the transition of the facility to owner operations.

Question 34

Under the Brooks Act, professional services of architects and engineers on federal projects must be

  1. contracted before GC services.
  2. funded by public dollars.
  3. qualification-based rather than bid.
  4. audited every six months.

Answer: C. qualification-based rather than bid.

The Brooks Act requires qualifications-based selection, not price bidding.