Question 31
In the typical design-bid-build delivery system, when the CM is evaluating risk for the owner during design, which of the following are the key risks to the owner?
Contractor and constructability
Quality and safety
Cost and schedule
Phasing and procurement
Question 32
A CM team on a new project which is the pre-design phase is planning their climate resiliency strategy. Which of the following is the team’s BEST first step in this process?
Hire a commissioning agent.
Collect relevant data and reports.
Establish a third-party certification.
Establish QA/QC specifications.
Question 33
One word or phrase to describe the process of transitioning from construction to permanent operations by the owner is
turnover.
O&M.
beneficial occupancy.
move-in.
Question 34
Under the Brooks Act, professional services of architects and engineers on federal projects must be