CMM: Certified Construction Manager practice questions, page 6 of 7, with answer review and explanations.
Question 26
Which of the following would MOST likely help provide benchmarking for a sustainable project?
Department of Transportation
Environmental Protection Agency
Housing and Urban Development
Energy Star program
Question 27
If it can be proven that there was discrimination based on gender during the hiring process, someone may lose their CCM credential due to a violation of the
CMAA Standards of Practice.
CMAA Code of Professional Conduct.
owner’s contract requirements.
owner’s diversity requirements.
Question 28
A construction contractor has an ongoing concrete operation and was planning on placing concrete for building footings today; however, the operation was called off due to rain and lightning. The affected activities have a Late Start of June 16th, an Early Start of June 15th, and Free Float value of 2. What is the slack value and is the contractor entitled to a weather impact day?
Slack value = 0, entitlement
Slack value = 1, no entitlement
Slack value = 2, no entitlement
Slack value = 3, no entitlement
Question 29
Which schedule process determines the earliest times that schedule activities can start and finish, and the total project duration?
Forward Pass
Schedule Update
Backward Pass
Master Schedule Review
Question 30
Which of the following is a key element of a safety culture?