Question 26

Which of the following would MOST likely help provide benchmarking for a sustainable project?

  1. Department of Transportation
  2. Environmental Protection Agency
  3. Housing and Urban Development
  4. Energy Star program

Question 27

If it can be proven that there was discrimination based on gender during the hiring process, someone may lose their CCM credential due to a violation of the

  1. CMAA Standards of Practice.
  2. CMAA Code of Professional Conduct.
  3. owner’s contract requirements.
  4. owner’s diversity requirements.

Question 28

A construction contractor has an ongoing concrete operation and was planning on placing concrete for building footings today; however, the operation was called off due to rain and lightning. The affected activities have a Late Start of June 16th, an Early Start of June 15th, and Free Float value of 2. What is the slack value and is the contractor entitled to a weather impact day?

  1. Slack value = 0, entitlement
  2. Slack value = 1, no entitlement
  3. Slack value = 2, no entitlement
  4. Slack value = 3, no entitlement

Question 29

Which schedule process determines the earliest times that schedule activities can start and finish, and the total project duration?

  1. Forward Pass
  2. Schedule Update
  3. Backward Pass
  4. Master Schedule Review

Question 30

Which of the following is a key element of a safety culture?

  1. Ownership and management buy-in
  2. Time is of the essence
  3. Maximizing profit
  4. Prompt accident notification