CMM: Certified Construction Manager

CMM: Certified Construction Manager practice questions, page 2 of 7, with answer review and explanations.

Get the full CMM practice test · 173 questions, PDF and online test engine

Question 6

A contractor is rehabilitating a bridge over a navigable waterway. The construction contract allows for the navigable channel to be closed for pier repairs for short durations, provided that the channel can be cleared within one hour of a Coast Guard request. Failure to do so will result in a hefty fine and project shutdown. The contractor decides to hire a tug boat with operator on standby for the length of the project to better facilitate swift removal of work barges from the channel. This scenario BEST describes use of which risk response?

  1. Avoidance
  2. Mitigation
  3. Escalate
  4. Accept

Answer: B. Mitigation

A standby tug reduces the likelihood and impact of delay penalties.

Question 7

When assembling a project schedule, the more typically used logic relationship is

  1. start to start.
  2. start to finish.
  3. finish to finish.
  4. finish to start.

Answer: D. finish to start.

Finish-to-start is the most common schedule relationship.

Question 8

The contract documents for a typical construction project include which of the following?

  1. Safety Requirements, Schedule, Specification, and Plans
  2. Permits, Standard Specifications, Drawings, and Pay Quantity Details
  3. Agreement, General Conditions, Technical Specifications, and Drawings
  4. Agreement, Change Order Process, Termination Clauses, and Plans

Answer: C. Agreement, General Conditions, Technical Specifications, and Drawings

Typical contract documents include agreement, conditions, specifications, and drawings.

Question 9

A client needs to deliver 50 distribution centers throughout the eastern United States. These will be time sensitive in their delivery and will need to open in a phased manner. Due to rising construction costs, the client wants to maximize as much of the economies of scale as possible. They have chosen to establish a Program Management Office (PMO) to drive this program. A CM’s firm has been selected to establish and operate this PMO. The contract requires key deliverables be established and met for the first 90 days of the PMO. Based on industry best practice, the CM establishes which of the following key deliverables initially?

  1. Meet with the owner and set program strategy; define program procedures; establish budgets and program baseline schedule.
  2. Meet with the owner; hire a contractor; begin work on the first 5 projects immediately.
  3. Hire one architect to be certain of consistency; hire a single contractor to ensure thorough understanding of the designs.
  4. Define space and functionality requirements, as well as operation and maintenance requirements; set safety, security, and quality standards.

Answer: A. Meet with the owner and set program strategy; define program procedures; establish budgets and program baseline schedule.

Initial PMO priorities include strategy, procedures, budgets, and baseline schedule.

Question 10

A construction project has been awarded at $85,000,000. There are also $15,000,000 in soft costs. Currently, $55,000,000 of work has been put in place and invoices in the amount of $12,500,000 of soft costs have been paid. The owner is expecting to add scope in the amount of $5,000,000 plus additional design fees of $85,000; however, the project is still expected to be completed on time. What is the estimate at completion?

  1. $37,585,000
  2. $100,000,000
  3. $105,000,000
  4. $105,085,000

Answer: D. $105,085,000

Remaining costs plus added scope and design fees total $105,085,000.

Get the full CMM practice test · 173 questions, PDF and online test engine