Question 61

Karen is the business analyst for her organization and she's reviewing the tasks within her endeavor. Several of the tasks have the characteristic that the activity will be completed with the project stakeholders, consultants, and business analyst, though this hasn't yet been approved. What is this condition of believing some things to be true about an activity without proving the validity of the belief called?

  1. Risk
  2. Assumption
  3. Constraint
  4. Boundary

Question 62

All of the following are examples of elicitation techniques that are used as part of the business analyst elicitation task except for which one?

  1. Brainstorming
  2. Observation
  3. Decomposition
  4. Prototyping

Question 63

You are the business analyst for your organization and you're preparing to elicit requirements from the stakeholders. You've gathered several inputs to help with the elicitation process. Which input(s) will be used to ensure that you understand the type of information that should be elicited from the stakeholders?

  1. Stakeholder list
  2. Risk assessment
  3. Business need
  4. Roles and responsibility

Question 64

You are a business analyst for your organization and you're working with the stakeholders to identify the primary inputs to the business analysis approach. Which one of the following is a primary input to the business analysis approach?

  1. The business analysis approach will be shaped by the problem or opportunity faced by the organization.
  2. The business analysis approach will be shaped by the penalty of not seizing the opportunity.
  3. The business analysis approach will be shaped by the time allowed for business analysis planning.
  4. The business analysis approach will be shaped by the risks faced by the organization.

Question 65

Your organization is using a plan-driven approach to business analysis. What must you do with all of the communication documents created as part of this high- priority project that you are serving as the business analyst for?

  1. The communications management plan will dictate what will happen to the business analysis communications.
  2. All formal communication must be destroyed once the project is completed.
  3. All communications must be archived and will become part of the organizational process assets.
  4. All communications must be documented and passed onto the solution's project manager for analysis and to serve as supporting detail.