Question 81
To which knowledge area does the Collect Requirements process belong?
- Quality Management
- Scope Management
- Cost Management
- Integration Management
Question 82
Which of the following can a project manager use to represent defined team member roles in a group of tasks?
- Work breakdown structure (WBS)
- Responsibility assignment matrix (RAM)
- Organizational breakdown structure (OBS)
- Resource breakdown structure (RBS)
Question 83
Under which circumstances should multiple projects be grouped in a program?
- When they are needed to accomplish a set of goals and objectives for an organization
- When they have the same project manager and the same organizational unit
- When they have the same scope, budget, and schedule
- When they are from the same unit of the organization
Question 84
How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?
- Monitor project stakeholder relationships using engaging strategies and plans
- Send all project documents to stakeholders each time they are modified
- Schedule monthly meetings with the stakeholders, including team members
- Engage only with the project sponsors
Question 85
Which are the competing constraints that a project manager should address when tailoring a project?
- Cost, scope, schedule
- Sponsorship, risk, quality
- Schedule, sponsorship, scope
- Resources, quality, communication