Question 81

To which knowledge area does the Collect Requirements process belong?

  1. Quality Management
  2. Scope Management
  3. Cost Management
  4. Integration Management

Question 82

Which of the following can a project manager use to represent defined team member roles in a group of tasks?

  1. Work breakdown structure (WBS)
  2. Responsibility assignment matrix (RAM)
  3. Organizational breakdown structure (OBS)
  4. Resource breakdown structure (RBS)

Question 83

Under which circumstances should multiple projects be grouped in a program?

  1. When they are needed to accomplish a set of goals and objectives for an organization
  2. When they have the same project manager and the same organizational unit
  3. When they have the same scope, budget, and schedule
  4. When they are from the same unit of the organization

Question 84

How can a project manager maintain the engagement of stakeholders in a project with a high degree of change?

  1. Monitor project stakeholder relationships using engaging strategies and plans
  2. Send all project documents to stakeholders each time they are modified
  3. Schedule monthly meetings with the stakeholders, including team members
  4. Engage only with the project sponsors

Question 85

Which are the competing constraints that a project manager should address when tailoring a project?

  1. Cost, scope, schedule
  2. Sponsorship, risk, quality
  3. Schedule, sponsorship, scope
  4. Resources, quality, communication