Question 76

The procurement requirements for a project include working with several vendors. What should the project manager take into consideration during the Project Procurement Management processes?

  1. Work performance information
  2. Bidder conferences
  3. Complexity of procurement
  4. Procurement management plan

Question 77

A project receives budget approval, but the risk of extra costs is expected. Which of these inputs should the project manager check in order to make a qualitative risk analysis?

  1. The risk management plan and the assumption log
  2. Costs estimates and cost forecasts
  3. The risk management plan and the basis of estimates
  4. The assumption log and the project charter

Question 78

What is one of the main purposes of the project charter?

  1. Formal authorization of the existence of the project
  2. Formal acceptance of the project management plan
  3. Formal approval of the detailed project budget
  4. Formal definition of stakeholder roles and responsibilities

Question 79

Tailoring considerations for project scope management may include:

  1. requirements management, stability of requirements, development approach, and validation and control.
  2. WBS guidelines, requirements templates, deliverable acceptance forms, and verified deliverables.
  3. business needs, product descriptions, project restrictions, and project management plan.
  4. issues defining and controlling what is included in the project, verified deliverables, and quality reports.

Question 80

Which of the following is a category of organizational process assets?

  1. Government standards
  2. Organizational culture
  3. Employee capabilities
  4. Organizational knowledge bases